Pools & Spas - Our Installation Process

Pools & Spas - Our Installation Process

Modern Pools

Different pool designs require different procedures, but in general, the following phases should be what you expect when the new pool construction starts. From start to finish, the whole process should take around 8 weeks.
1 Design Phase
Our professional designers will work with you to come up with the best possible design for your home. What you always envisioned. The design is complete, includes landscaping, accessories like fire place or a fire ring, Sod or artificial grass, decking, spa and water falls.
  Install Process
 
Install Process   2 The Digging Phase
After your are 100% satisfied with the design, we obtain permits from engineering and the city. We also call dig alert to mark any underground pipes. On the designated start date, we mark the grounds, and set the leveling. Our excavating team goes at it. This phase usually takes 1 day to complete.
 
3 Steel Rebar Phase
Usually the next day after excavating, our steel rebar team goes to work. Thismphase also usually takes 1 day to complete.
  Install Process
 
Install Process   4 Equipment, Plumbing, Gas and Electrical Phase
Usually right after the steel rebar is installed, our team of plumbers and electricians start installing the water lines, electrical, gas and equipment lines. This phase usually takes 5 days to complete.
 
5 Gunite/Shotcrete Phase
As soon as the plumbing phase is completed, we call for inspection. Once the inspection is signed off, the next day we shoot gunite or shotcrete. This phase also usually takes 1 day to complete. We let the fresh gunite Cure for 7 days.
  Install Process
 
Install Process   6 Coping and Tile Phase
After the pool has cured for 7 days, we start on the coping, then the tile. Depending What kind of coping you choose, this process will take 3 to 5 days to complete. Concrete Precast coping is shown below.
 
7 Decking Phase
Once the coping and tile are done, we start preparing the deck. We install steel rebar Bonding grid, drains and any other conduits, we call for pre-deck inspection, and proceed with the decking process. Depending on the kind of deck you choose, installing the deck takes 2 to 5 days to complete. 5 piece interlocking paving stones are shown below.
  Install Process
 
Install Process   8 Plaster Phase
Once the deck is installed, we call for pre plaster inspection. Then we proceed with the plastering process. This takes 1 day to complete. Once plaster is complete, we start filling the pool with water. Depending on the size of the pool, time needed to fill the pool varies.
 
9 Enjoy